Ships under construction and accepted as of 28.07.2013 for the Russian Navy. Part 1

Table of contents:

Ships under construction and accepted as of 28.07.2013 for the Russian Navy. Part 1
Ships under construction and accepted as of 28.07.2013 for the Russian Navy. Part 1

Video: Ships under construction and accepted as of 28.07.2013 for the Russian Navy. Part 1

Video: Ships under construction and accepted as of 28.07.2013 for the Russian Navy. Part 1
Video: This New Russian TOR Air Defense System Is A Real Threat To NATO 2024, April
Anonim

This article contains the most complete list of ships and vessels for the Russian Navy that were handed over and undergoing tests in 2013, as well as a list of those under construction since the moment of laying. Ships and vessels ordered but not mortgaged were not included in the list. Each ship is equipped with the latest information, displacement and purpose or weapons. The latter is indicated for those who have little knowledge of the fleet. For those who are in a hurry, 7 frigates are currently being built, 6 corvettes of which two are from UKSK (1 was transferred this year), 5 MRKs from UKSK (1 was transferred this year), 5 diesel submarines, 3 multipurpose nuclear submarines of the latter generations (1 being transferred this year), 4 strategic missile cruisers (possibly 3 will be transferred this year), 1 special nuclear submarine, a host of other combat and auxiliary ships in total more than 80!

List of accepted and built ships (stage of sea trials and above) in 2013

Corvette pr. 20380 Boykiy, construction of the Northern Shipyard according to the Almaz project, the flag was raised on May 16, 2013, transferred to the Baltic Fleet:

Image
Image

Displacement - 2200t

Armament - SAM "Redut" 12 missiles 9M96 (up to 50 km range) or 9M100 4 in 1 cell (up to 12 km range), SCRC "Uran" with 8xX-35 (130 km range), Packet-NK 8x330 mm torpedoes, A -190 100 mm cannon, 2 30 mm AK-630 assault rifle and 2 MTPU 14.5 mm machine gun mount. There is a helicopter in the hangar, a GAS in a bulb, a Minotaur-M towed and an Anapa-M descent.

Small rocket ship, project 21631 Grad Sviyazhsk, built at the Zelenodolsk plant according to the design of the Zelenodolsk Design Bureau, for the Caspian Flotilla. On June 17, the ship was sent to Astrakhan at the place of service; from July 10, it is undergoing a complex of state tests.

Image
Image

Displacement - 950t

Armament - UKSK-8 with missiles of the Caliber complex (3M-54, 3M-14, 91R / T) and Onyx with a range of over 2000 kilometers on a ground target (according to the CFL commander in relation to Dagestan, which has the same complex) and 350 surface. Two 3M47-01 air defense systems Bending with Igla missiles, A-190 100 mm cannon, 1 30 mm AK-630M-2 Duet submachine gun, 2 MTPU 14, 5 mm machine gun mount.

Anti-sabotage boat, project 21980 P-350, designed by Vympel Design Bureau, built at the Zelenodolsk plant. On June 24, 2013 he was sent from the plant to Novorossiysk to undergo state tests and serve in the Black Sea Fleet.

Ships under construction and accepted as of 28.07.2013 for the Russian Navy. Part 1
Ships under construction and accepted as of 28.07.2013 for the Russian Navy. Part 1

Displacement - 140t

Armament - MTPU 14, 5 mm machine gun mount, Igla-S MANPADS 4 pieces, anti-sabotage grenade launchers DP-65A and DP-64. To detect saboteurs and small underwater vehicles, they use GAS Kalmar and the descent Anapa, there is an optoelectronic observation complex and the necessary equipment for accommodating divers.

Anti-sabotage boat pr. 21980 head. # 985, designed by Vympel Design Bureau, built at the Zelenodolsk plant. On July 26, 2013 he was sent to Astrakhan to serve in the Caspian Flotilla.

Image
Image

Landing boat pr. 11770 Serna produced by the Volga Shipyard in Nizhny Novgorod, designed by the Central Design Bureau for the SPK im. R. E. Alekseeva. The first boat was tested on May 28, 2013, and is waiting at the factory for the second one to be sent to the place of service as part of the Caspian Flotilla.

Image
Image

Displacement - 100t

Holds up to 45 tons of cargo, 1 MBT, 2 armored personnel carriers or trucks, 92 marines with weapons. Speed up to 30 knots and range up to 100 miles at full speed or 600 at an economical 12 knot speed with waves up to 3 balls.

Small hydrographic vessel "Victor Faleev" pr. В19910, built by Vostochnaya Verf OJSC according to the project of Vympel Design Bureau signing of the acceptance act on January 26, raising the flag on April 27, 2013, transferred to the Pacific Fleet.

Image
Image

Displacement - 1000t

The equipment is a multi-beam echo sounder of the latest generation, which allows obtaining a volumetric image of the bottom relief directly during hydrographic work. This is the first equipment of this type in the Pacific Fleet, which allows the processing of research results in real time in 3D format.

Diving boat pr. 14157 built by Blagoveshchenskiy OJSC "Shipbuilding Plant of the October Revolution", according to the design of KB Vympel, launched on May 8, 2013, has been undergoing tests since June 2013. The boat was built for the needs of the Pacific Fleet. According to official information from the plant, the second boat is 70% ready. It is also planned to be launched at the end of May, but there are no photos of the launch or any other data about it.

Image
Image

Displacement - 80t

Equipment - the boat has a hydraulic crane for lifting cargo from depth and is equipped with a pressure chamber, there is all the necessary equipment for divers to work in various equipment.

Harbor tug RB-396, project 705B built by the Astrakhan shipyard according to the design of KB Vympel. The tug was accepted into the Caspian flotilla on May 14, 2013.

Image
Image

Displacement - 360t

Power - traction force on the hook of 30 tons, capable of towing any ship of the Caspian flotilla.

Ice-class escort tug, project PE-65 (Ice2 - Arc4) MB-92, built by Pella shipyard according to its own design. Adopted on May 30, 2013, transition to the Pacific Fleet is expected.

Image
Image

Displacement - 860t

Equipment - the ability to carry out all operations towing, escorting and tilting any ships with a displacement of up to 100,000 tons. The pull on the hook is 65t, and the retention during escorting is 76t.

Ice-class escort tug, project PE-65 (Ice2 - Arc4) MB-93, built by Pella shipyard according to its own design. Adopted on May 2, 2013, transition to the Pacific Fleet is expected.

Image
Image

Tug of project 16609 (Ice2-Arc4) RB-402 (621), built by Pella shipyard according to its own design. At the moment, it is being tested under order number 621. It is expected that a delivery package for transportation to the Pacific Fleet will be formed in September.

Image
Image

Displacement - 504t

Capabilities - thrust force 39-54t, can operate at a distance of 100 miles from the coast, escort at speeds up to 10 knots, can be used to remove ships and vessels aground, extinguish fires on floating objects and onshore facilities, participate in OSR operations, transport goods washing away ice.

Harbor tug, project 16609 (Ice2-Arc4) RB-403 (No. 622), built by Pella shipyard according to its own design. At the moment, it is being tested under order number 622. It is expected that a delivery package for transportation to the Pacific Fleet will be formed in September.

Image
Image

Harbor tug, project 16609 (Ice2-Arc4) RB-404 (No. 623), built by Pella shipyard according to its own design. It is undergoing state tests. It is expected that in September a delivery package will be formed for transportation to the Pacific Fleet.

Image
Image

Harbor tug, project 16609 (Ice2-Arc4) RB-405, built by Pella shipyard according to its own design. It is undergoing state tests. It is expected that in September a delivery package will be formed for transportation to the Pacific Fleet.

Image
Image

Harbor tug, project 90600 (Ice2-Arc4) RB-392, built by Pella shipyard according to its own design. Commissioned on June 6, 2013, transferred to the Black Sea Fleet at the Naval Base Novorossiysk, crossing by internal routes.

Image
Image

Displacement - 417t

Opportunities - thrust force 23-35t, escorting at speeds up to 10 knots, can be used to remove ships and vessels from aground, extinguish fires on floating objects and onshore facilities, participate in OSR operations, transport cargo, wash ice.

Harbor tug, project 90600 (Ice2-Arc4) RB-398, built by Pella shipyard according to its own design. Launched on March 7, 2013, according to the latest news, in June it began sea trials, transferred to the Black Sea Fleet in the Novorossiysk naval base, crossing by internal routes.

Image
Image

Harbor tug of project 90600 (Ice2-Arc4) RB-399 (No. 937), built by Pella shipyard according to its own design. Launched on May 18, 2013, started sea trials in July, transferred to the Northern Fleet, dispatch of the tug in autumn 2013.

Image
Image

Non-self-propelled floating target (large ship's shield) of the catamaran type, project 436B, produced by the Sokolsk shipyard, launched on July 2, 2013, the target is being accepted by the military department, until the end of summer it will be towed to the place of service.

Image
Image

Displacement - 142t

The lead nuclear submarine, project 885 K-560 "Severodvinsk", built by Sevmash and designed by SPMBM "Malakhit". At the moment, the ZHI has been completed and the boat was transferred to the GSE on June 2, 2013, it is planned to put it into operation this year, and will be transferred to the Northern Fleet.

Image
Image

Displacement - 8 600/13 800 t

Armament - 8 quadruple mines for the Caliber complex and 10,533 mm TA.

The head nuclear submarine missile cruiser of a strategic purpose, project 955 K-535 "Yuri Dolgoruky", built by Sevmash according to the design of the Central Design Bureau MT "Rubin". On January 10, 2013, the flag was raised, the submarine missile carrier was enrolled in the 31st division in the Hajiyev Northern Fleet.

Image
Image

Displacement - 14 720/24 000 t

Armament - 16 intercontinental missiles R-30 Bulava, 6 533 mm TA.

The first serial nuclear-powered strategic missile cruiser, project 955A K-550 "Alexander Nevsky", built by Sevmash under the design of CDB MT "Rubin". According to Mikhail Budnichenko, general director of the Severodvinsk shipyard Sevmash, the first serial strategic nuclear submarine of Project 955 Borey will be handed over to the Russian fleet on November 15, 2013. The ship is now undergoing government tests, with rocket firing scheduled for September 2013.

Image
Image

Serial nuclear-powered strategic missile cruiser, project 955A K-550 "Vladimir Monomakh", built by Sevmash according to the design of the Central Design Bureau MT "Rubin". Yes, I do not believe that it will be handed over this year. However, let us turn to the available information. On May 23, 2013, the landmark stage of mooring tests was successfully completed, the steam turbine unit was tested at full capacity. Already in July-August, the cruiser should go to sea trials. In his interview on July 5, 2013, Mikhail Budnichenko said the following - As Budnichenko specified, the second serial Borey, that is, the third in a row - Vladimir Monomakh - is currently completing mooring tests. "He went through the demagnetization procedure. On July 29 - right after the Fleet Day - he will go out to the factory sea trials in the White Sea, to the proving grounds, where it should be," he said. "The end of the factory running state tests is planned for December 12. On December 25 - 27 we hope to sign an acceptance certificate on its transfer to the Russian Navy," said the head of Sevmash.

Image
Image

Modernization:

Diesel-electric submarine of pr. 877LPMB according to the design of the Central Design Bureau MT "Rubin", medium repair and modernization was performed by Zvezdochka. On July 9, 2013, the boat was transferred to the Northern Fleet. In addition to repairs, a comprehensive modernization was carried out, in particular:

Installed hydroacoustic complex - MGK-400V.1;

A combat information management system - MVU-100EM was installed;

Installed navigation complex - Andoga-M;

Installed rechargeable battery - AB476.

Image
Image

Displacement - 2300 / 3040t

Armament - 6 533 mm TA

Construction for the needs of the Russian Navy:

The lead frigate of project 22350 Admiral of the Fleet of the Soviet Union Gorshkov, being built at the Severnaya Verf according to the project of the Severny PKB. Completed at the wall of the Northern Shipyard. A number of units have not yet been assembled, such as the Polyment canvases, the BIUS Linkor-22350 and the A-192 cannon (however, it was transferred to the plant). It is planned to start testing this year, and transfer the frigate in 2014. However, many agree that the actual combat unit will be transferred no earlier than 2015.

Image
Image

Displacement - 4500t

Armament - 2 UKSK-8 missiles of the Caliber complex (3M-54, 3M-14, 91R / T) and Onyx with a range of over 2000 kilometers at a ground target (according to the CFL commander in relation to Dagestan, which already has the same complex) and 350 on the surface. SAM "Polyment-Redut" with 32 missiles 9M96E2 (range up to 150 km) or 9M100 (range 12 km), 4 in one cell. Package-NK 8x330 mm torpedoes. Cannon 130mm A-192 Cartown and 2 ZRAK Broadsword. Helicopter with a hangar.

Serial frigate of the project Admiral of the Fleet Kasatonov, being built at the Severnaya Verf according to the project of the Severny PKB. The compartments are being saturated, the turbines are being installed and preparations are underway for the launch, which is to take place this year. Delivery 2015.

Image
Image
Image
Image

Serial frigate of project 22350 Admiral Golovko, being built at Severnaya Verf according to the project of Severny PKB. Laid down on February 1, 2012. The body is being formed, in particular, the fourth block of the body is assembled, the first and second blocks are being formed, the fifth and ninth have begun to be made and the metal is cut into the eighth block.

Image
Image

Project 11356 lead frigate Admiral Grigorovich, built by Shipyard Yantar according to the Northern Design Bureau for the Black Sea Fleet. It is being built on an open slipway, compartments are rented for constructiveness, according to various information, including the factory newspaper B! The descent is scheduled for early autumn 2013.

Image
Image

Displacement - 4000t

Armament - UKSK-8 with missiles of the Caliber complex (3M-54, 3M-14, 91R / T) and Onyx with a range of over 2000 kilometers on a ground target (according to the CFL commander in relation to Dagestan, which already has the same complex) and 350 on the surface. SAM VPU Calm for 36 missiles (range 50 km). 2x2 533 mm TA, RBU-6000. Cannon 100mm A-190, 2 AK-630M. Helicopter with a hangar.

Serial frigate of project 11356 Admiral Essen, built by Shipyard Yantar according to the project of the Northern Design Bureau for the Black Sea Fleet. It is being built on an open slipway, the compartments are being rented for constructiveness, the descent is in the spring of 2014.

Serial frigate of project 11356 Admiral Makarov, built by Shipyard Yantar according to the project of the Northern Design Bureau for the Black Sea Fleet. It is being built in a covered boathouse, the hull is being recruited, the descent is planned for 2014, but in reality it is unlikely.

Image
Image

Serial frigate of project 11356 Admiral Butakov, built by Shipyard Yantar according to the project of the Northern Design Bureau. Laid down on July 12, 2013, as a result of the relocation of the tab, the plant workers have already gained a rather impressive hull section, others are also in work. Under construction in a covered boathouse, descent according to plan 2015.

Image
Image
Image
Image

Serial corvette of project 20380 Resistant, built by Severnaya Verf according to the Almaz project. The building is being completed at the wall, the artillery installation and the Redoubt have been shipped, the systems are being installed. It is planned to enter trials by the end of 2013, the transfer to the Baltic Fleet will be made in 2014 (photo of May 2012, not later).

Image
Image

Displacement - 2200t

Armament - SAM "Redut" 12 missiles 9M96 (up to 50 km range) or 9M100 4 in 1 cell (up to 12 km range), SCRC "Uran" with 8xX-35 (130 km range), Packet-NK 8x330 mm torpedoes, A -190 100 mm cannon, 2 30 mm AK-630 assault rifle and 2 MTPU 14.5 mm machine gun mount. There is a helicopter in the hangar, a GAS in a bulb, a Minotaur-M towed and an Anapa-M descent.

Serial corvette of project 20380 Perfect, construction of the Amur shipyard according to the Almaz project. The superstructure is being installed and preparations are underway for launching, the descent of the ship is scheduled for 2014, the transfer of the corvette to the Pacific Fleet is also scheduled for 2014, but this seems unlikely.

Image
Image
Image
Image

Serial corvette of project 20380 Loud, built by the Amur shipyard according to the Almaz project. The hull is being formed, launching in 2015 (laid down in April 2012).

Image
Image

The head corvette of Project 20385 Thundering, built by Severnaya Verf according to the Almaz project. The hull has been formed, its filling is in progress, a superstructure is expected, after which the ship will be launched. This will happen in 2014.

Image
Image

Displacement - 2600t

Armament - UKSK-8 with missiles of the Caliber complex (3M-54, 3M-14, 91R / T) and Onyx with a range of over 2000 kilometers on a ground target (according to the CFL commander in relation to Dagestan, which already has the same complex) and 350 on the surface. SAM "Redut" 2x8 (total 16) 9M96 / E2 missiles (up to 50/150 km range) or 9M100 4 in 1 cell (up to 12 km range), Packet-NK 8x330 mm torpedoes, A-190 100 mm cannon, 2 30 mm AK-630 assault rifle and 2 MTPU 14, 5 mm machine gun mount. There is a helicopter in the hangar, GAS Zarya-2 in the bulb, towed by the Minotaur-M and the descent Anapa-M.

Serial corvette of project 20385 Agile, built by Severnaya Verf according to the Almaz project. Laid down at Severnaya Verf on July 25, 2013. Estimated completion date 2016.

Image
Image

To the left of the thundering stern:

Image
Image

Serial small missile ship, project 21631 Uglich, built at the Zelenodolsk plant according to the design of the Zelenodolsk Design Bureau, for the Caspian Flotilla. The ship was launched on April 10, 2013, in the fall it is planned to cross to the Caspian by inland waterways for state tests and inclusion in the flotilla.

Image
Image

Displacement - 950t

Armament - UKSK-8 with missiles of the Caliber complex (3M-54, 3M-14, 91R / T) and Onyx with a range of over 2000 kilometers on a ground target (according to the CFL commander in relation to Dagestan, which has the same complex) and 350 surface. Two 3M47-01 air defense systems Bending with Igla missiles, A-190 100 mm cannon, 1 30 mm AK-630M-2 Duet submachine gun, 2 MTPU 14, 5 mm machine gun mount.

Serial small rocket ship, project 21631 Veliky Ustyug, being built at the Zelenodolsk plant according to the design of the Zelenodolsk Design Bureau, for the Caspian Flotilla. The corps has been formed, the saturation and installation of weapons is underway. Launching is scheduled for autumn 2013.

Image
Image

Serial small rocket ship, project 21631 Zelyoniy Dol, being built at the Zelenodolsk plant according to the design of the Zelenodolsk Design Bureau, for the Caspian Flotilla. The corps is being formed, joining the Navy in 2014.

Image
Image

Serial small missile ship, project 21631 Serpukhov, being built at the Zelenodolsk plant according to the design of the Zelenodolsk Design Bureau, for the Caspian Flotilla. Laid down on January 25, 2013, the corps is being formed. Delivery of the ship in 2015.

Image
Image

Base minesweeper of project 12700 "Alexandrite" BT-730 under construction in Sredne-Nevsky SZ according to the project of FSUE TsMKB "Almaz". The hull has been cast, according to an innovative molding technology, preparations are underway for launching. Manual monetary management slows down the process (Alexandrite was excluded from the GPV, now it is included in the new one, however, based on the results of tests of the head one), but they promise to send it for testing in 2014.

Image
Image
Image
Image

Displacement - 720t.

Anti-sabotage boat, project 21980 No. 986, designed by Vympel Design Bureau, built at the Zelenodolsk plant. Bookmarked on May 7, 2013. Delivery is expected at the end of next year.

Image
Image
Image
Image

Displacement - 140t

Armament - MTPU 14, 5 mm machine gun mount, Igla-S MANPADS 4 pieces, anti-sabotage grenade launchers DP-65A and DP-64. To detect saboteurs and small underwater vehicles, they use GAS Kalmar and the descent Anapa, there is an optoelectronic observation complex and the necessary equipment for accommodating divers.

Anti-sabotage boat, project 21980 No. 987, designed by Vympel Design Bureau, built at the Zelenodolsk plant. Bookmarked on July 27, 2013, this boat is jubilee, 10th of this project.

Image
Image

Anti-sabotage boat pr. 21980 No. 8002, designed by Vympel Design Bureau, built at Vostochnaya Verf. Launched on June 24, 2013, they promise to transfer it to the Pacific Fleet this year, we'll see.

Image
Image

Anti-sabotage boat pr. 21980 No. 8003, designed by Vympel Design Bureau, built at Vostochnaya Verf. It is under construction, rolled out into the air, but this year it is unlikely to be handed over, maximum to be launched.

Image
Image

Anti-sabotage boat, project 21980 No. 8004, designed by Vympel Design Bureau, built at Vostochnaya Verf. Laid down, the formation of the hull and its saturation are underway, transfer to the Pacific Fleet in 2014.

Image
Image

The second part follows, there is also a lot of interesting things.

Recommended: